Denny Lenth has been helping people realize their dream of home ownership since 1979. From selling and investing to building spec and custom homes, his rule has always been the same: treat people fairly and honestly, give them good value and never compromise quality.
As President of Denny Lenth Construction, Denny oversees every step of your home's progress. From the initial meeting to the final walk-through prior to closing and the subsequent follow-up during the warranty period.
I. Pre-Construction
Secure lot
Develop and finalize blue prints
Finalize interior and exterior specs
Prints and specs to subs for bid
Appraisal
Site plan and blue print to City for permit
Print to Utilities for Common Sense Program
Close on construction loan
Sign construction contract, blue print, spec
Check for non-refundable deposit
II. Excavation
Water/Sewer
Break ground
Footings/Walls
Tile (footing), egress - windows
Rub-R-Wall
Backfill
III. Framing
Plate/Floor package
Stud package
Sheathing package
Plumbing: bath bays, etc.
Roof trusses
Roof sheathing
Felt/Flash/Winter Guard
Shingle
Windows/Doors
Frame outside basement walls
Bracing
Soffits
Deck ledger board
Scuttles
Backer/Drapes, etc
Fireplace
IV. Siding
Materials/Accessories
Labor
V. Exterior Brick/Stone
VI. Plumbing
Basement rough-in
Bath bays/Shower Stall/Whirlpool
Above grade rough-in
Final plumbing - Fixtures/Lavs/Faucets
Water heater
Water softener
Plumb dishwasher
VII. Heating/Cooling
Rough in
Furnace
Central air
Registers
Fireplace
Dryer vent
Gas meter
VIII. Electrician
Rough wire/Recessed
Permanent electric
Smoke detector/TV/Telephone
Final fixtures
IX. Flatwork
Basement floor
Soak garage prior to pouring
Garage/Stoop
Driveway
Service walks
Patios/Pads, etc.
X. Drywall
XI. Garage Floors
XII. Painters
Prime
Enamel
Stain/Seal/Varnish
Exterior doors
Grain
Built-ins
Exterior trims
XIII. Fireplace Masonry
XIV. Insulation
Air & Wall package
Attic
Special
XV. Gutters/Downs/Extensions
XVI. Finish Carpenter
Set/Hang cabinets
Hang doors
Closet shelving
Base/Casing
Set counter tops
Cut holes - sinks
Crown/Chair mould
Stair system
Built-ins
Bath accessories
Fireplace mantle/Built-ins
Door hardware/Stoops
Porch/Screened Porch/Deck
XVII. Yard Work
Final rough grade
Shovel grade
Rock/Visqueen deck
Landscape/Trees
Retaining walls
Fine grade
Irrigation system
Sod
XVIII. Floor Coverings
Carpet/Wood/Tile/Vinyl
Special
XIX. Miscellaneous
Mirrors
Mailbox
Wallpaper
House cleaning
Kitchen appliances
Sound system
Security system
XX. Closing
Occupancy inspection
Final walk-through
Punch lists
Funds withheld for work not completed
Warranty agreement signed
Final payment before move-in
|
|
|
|